Daily Summary

OCTOBER 2003

Previous page

DATE
WORK

Hours
Peter

Hours
Ian
Hours
Others
Daily
Total
Running
Total
Brought forward   354.5 405.5  14.5  - 774.5
02/10/03 mass balance arm cables 2 4 - 6 780.5
04/10/03 set up for undercarriage 6 5 - 11 791.5
06/10/03 install brakes .5 3 - 3.5 795
07/10/03 undercarriage holes and set up 2.5 - - 2.5 797.5
08/10/03 ditto 2.5 - - 2.5 800
09/10/03 bond straightedge to floor 1.5 1.5 - 3 803
10/10/03 bond u/c tubes 1 1 - 2 805
11/10/03 u/c ribs 3 2 - 5 810
13/10/03 ditto 1 2 - 3 813
14/10/03 u/c rib layups 2 2 - 4 817
16/10/03 ditto, plus wing inspection and misery 3 2 - 5 822
20/10/03 u/c ribs 1 3 - 4 826
21/10/03 ditto 2 - - 2 828
22/10/03 ditto 3 2 - 5 833
23/10/03 ditto 2 - - 2 835
25/10/03 rib lay ups - 3 - 3 838
27/10/03 ditto - 2 - 2 840
29/10/03 ditto - 2 - 2 842
31/10/03 ditto - 2 - 2 844
  TOTALS 387.5 442 14.5    