Daily Summary

December 2002

Previous page

DATE
WORK

Hours
Peter

Hours
Ian
Hours
Others
Daily
Total
Running
Total
Brought forward   14.5 19.5 - 34
1/12/02
Organising tools etc
4 - - 4 38
5/12/02
Wheels & brakes/cockpit
2 7   9 47
7/12/02
Cockpit cutouts/trim assembly
6 5   11 58
14/12/02
Rebuild work bench
6 5   11 69
15/12/02
Sort out mess left by Ian
3 -   3 72
16/12/02
Meet inspector. Get acetone. Fit Flap bushes
1 3   4 76
17/12/02
Build jig for tail plane then throw it away. See Update page.
- 2   2 78
19/12/02 Prepare for lay up of flap close out/ visit local builder for encouragement and advice. 6 7   13 91
20/12/02 Flap tip close out - 1.5   1.5 92.5
23/12/02 Flap close outs and general swearing 4.5 - - 4.5 97
27/12/02 Flap & Aileron close outs - 5   5 102
29/12/02 Repaired flap close outs. Finished aileron roots. 6.5 6.5   13 115
31/12/02 Filed flaps and made aileron mass balance templates - 3   3 118
  TOTALS 53.5 64.5      