Daily Summary

AUGUST 2003

Previous page

DATE
WORK

Hours
Peter

Hours
Ian
Hours
Others
Daily
Total
Running
Total
Brought forward   273.5 310.5  2.5  - 586.5
05/08/03 finalise wings 2 4 - 6 592.5
07/08/03 ditto - 2 - 2 594.5
09/08/03 prepare fuselage and collect rotating stand 5.5 5 - 10.5 605
10/08/03 Inspection hatches 1.5 1.5 - 3 608
12/08/03 Dolly refurbishment 1 - - 1 609
14/08/03 Cockpit module prep 1.5 - - 1.5 610.5
16/08/03 ditto 5 5 - 10 620.5
17/08/03 Bonding in the cockpit module 5.5 5.5 10 21 641.5
18/08/03 Wing spar openings 1.5 - - 1.5 643
19/08/03 Module/firewall layups .5 3 - 3.5 646.5
20/08/03 Engine mount prep 2.5 3 - 5.5 652
21/08/03 ditto, plus spar aperture layups 3.5 4 - 7.5 659.5
23/08/03 Bonded new plates for engine mount 5 5 - 10 669.5
26/08/03 Layup cockpit to firewall 1.5 - - 1.5 671
29/08/03 Installation of engine mount - 4 - 4 675
30/08/03 Rudder pedals and cockpit floor 5 5 - 10 685
31/08/03 Repair to cockpit floor .5 - .5 .5 686
  TOTALS 315.5 357.5 13    